Huaxu Aotong HZS120 Concrete Mixing Station Installation Progress Update:
Today, the installation work progressed smoothly. The spiral port opening operation was successfully completed. Concurrently, the installation and securing of the dust collection pipes and butterfly valves were finished. Additionally, the lashing, binding, and commissioning of the dust filter bags, as well as the assembly and positioning of components related to the admixture system, were all accomplished.Currently, the water pipeline welding process is not yet fully completed. Further optimization and adjustments to the welding techniques and pipeline layout will be carried out subsequently to ensure the stable operation of the system.