As of now, the relevant construction of the screw feeding port, drain pipe, middle storage bin rubber sheet and inclined belt of the HZS180 Concrete Mixing Station Project of No.14 Hydroelectric Engineering Bureau in Enshi has been fully completed, accounting for 42% of the total project progress, and the remaining core equipment installation and system commissioning are advancing as planned.