搜索信息

Oasis News
Home > Oasis News

Kazakhstan 180 Batching Plant Project Advances Efficiently

2025-10-10

The Kazakhstan 180 batching plant project, undertaken by Xinjiang Oasis Machinery Co., Ltd., has been progressing rapidly since its commencement. With the equipment storage area located far from the installation site, the on-site team promptly organized a "secondary transfer" in the morning, accurately transporting the required components to the hoisting points, thereby clearing obstacles for subsequent work. In the afternoon, installation work accelerated significantly, with the successful hoisting and positioning of the first level of the main plant building. Simultaneously, the assembly of the cement silo group proceeded efficiently. The team successfully completed the assembly of the "first cone" and "second cone" sections of two cement silos, as well as the "third cone" section of one cement silo, with the three large silos now taking initial shape. This demonstrates the exceptional technical skills and efficient collaboration of the Xinjiang Oasis Machinery team.



© 2026 Xinjiang Oasis Machinery Co., Ltd  All Rights Reserved. 腾云建站仅向商家提供技术服务